Below are the dates for activities related to ETL2. ETLs (Export, Transform, Load) are project phases during which data is Exported from the legacy system, it is then Transformed (or converted) and Loaded it into the new Anthology Student system. Once these steps are completed testing begins.
Please be aware that the dates and activities listed below are subject to change and we will do our best to communicate changes in a timely manner.
| Activity | Start | End | Details |
|---|---|---|---|
| Data is extracted from CX | October 21 | October 25 | 10/21/2024 is the effective date of the data in ETL2. |
| Delta mapping | October 24 | October 28 | No action for 5C testers. The Project Team completes this activity. |
| Prod is copied to Test | October 27 | October 28 | No action for 5C testers. |
| No access to Prod environment | October 28 | October 28 | No action for 5C testers. |
| No access to Test environment | October 28 | November 1 | No action for 5C testers. |
| Project Team testing | November 11 | December 13 | No action for 5C testers. The Project Team will complete configuration and data validation. |
| ETL2 Kickoff | November 18 at 9am | November 18 at 10am | An MS Teams meeting from 9am to 10am (Pacific Time) with the Anthology team to review ETL2 testing procedures and activities. |
| Student Accounts testing | November 18 | November 21 | Coordinated completion of test cases for Student Accounts on student control groups, processes, and reports. |
| Registrar “Testing Hours” | November 18 | December 13 | Coordinated completion of test cases for Registrars (academic records) on student control groups, processes, and reports during daily Testing Hours. Times for Testing Hours to be determined by the 5CRC. |
| Issue resolution | November 18 | December 20 | Issue resolution begins with the submission of issues and is ongoing through the ETL. Some issues may continue into January. |